Solving Permutation Flow Shop Scheduling Problem with Sequence-Independent Setup Time
Open Access
- 22 January 2020
- journal article
- research article
- Published by Wiley in Journal of Applied Mathematics
- Vol. 2020, 1-11
Abstract
In this paper, we study the resolution of a permutation flow shop problem with sequence-independent setup time. The objective is to minimize the maximum of job completion time, also called the makespan. In this contribution, we propose three methods of resolution, a mixed-integer linear programming (MILP) model; two heuristics, the first based on Johnson’s rule and the second based on the NEH algorithm; and finally two metaheuristics, the iterative local search algorithm and the iterated greedy algorithm. A set of test problems is simulated numerically to validate the effectiveness of our resolution approaches. For relatively small-size problems, it has been revealed that the adapted NEH heuristic has the best performance than that of the Johnson-based heuristic. For the relatively medium and large problems, the comparative study between the two metaheuristics based on the exploration of the neighborhood shows that the iterated greedy algorithm records the best performances.Keywords
This publication has 54 references indexed in Scilit:
- Minimizing the total completion time in a two-machine flowshop with sequence-independent setup timesJournal of the Operational Research Society, 2012
- New MILP models for the permutation flowshop problemJournal of the Operational Research Society, 2008
- Comparative evaluation of MILP flowshop modelsJournal of the Operational Research Society, 2005
- Improved genetic algorithm for the permutation flowshop scheduling problemComputers & Operations Research, 2004
- Two MILP models for the N × M SDST flowshop sequencing problemInternational Journal of Production Research, 2001
- Genetic algorithms for flowshop scheduling problemsComputers & Industrial Engineering, 1996
- Simulated annealing for permutation flow-shop schedulingOmega, 1989
- Comparison of heuristics for flow shop sequencingOmega, 1987
- A heuristic algorithm for the m-machine, n-job flow-shop sequencing problemOmega, 1983
- Optimal two‐ and three‐stage production schedules with setup times includedNaval Research Logistics Quarterly, 1954