Flexible job-shop scheduling problem with unrelated parallel machines and resources-dependent processing times: a tabu search algorithm
Authors:
- 6 July 2021
- journal article
- research article
- Published by Taylor & Francis in International Journal of Management Science and Engineering Management
- Vol. 16 (4) , 242-253
Abstract
Flexible job shop scheduling problem is one of the most important topics in production management and is one of the most complex topics in combinatorial optimization. This problem is a generalization of job shop and parallel machines scheduling problem. Since the efficient allocation of resources can improve the performance of manufacturing, here, to reduce the processing time of jobs, additional resources are assigned to machines. In fact, in this paper, the effect of flexible resources in the flexible job shop scheduling problem with unrelated parallel machines and sequence-dependent setup time is investigated. Also, by presenting a mixed-integer linear programming model, an attempt has been made to minimize the costs of makespan, total weighted tardiness, delivery time and inventory. After solving this model by the GAMS, due to the NP-hardness of the problem, a tabu search (TS) algorithm is utilized for large-size instances. Finally, the obtained results are compared with the genetic algorithm (GA). To verify the statistical validity of the computational experiments and confirm which the best algorithm between the TS algorithm and GA is, a Kruskal–Wallis test is used. The results show that the TS algorithm is better than the GA.Keywords
This publication has 45 references indexed in Scilit:
- Dispatching rules for unrelated parallel machine scheduling with release datesThe International Journal of Advanced Manufacturing Technology, 2013
- Solving job shop problems in the context of hypergraphsCentral European Journal of Operations Research, 2012
- A discrete colonial competitive algorithm for hybrid flowshop scheduling to minimize earliness and quadratic tardiness penaltiesExpert Systems with Applications, 2011
- Hybrid flowshop scheduling with machine and resource-dependent processing timesApplied Mathematical Modelling, 2011
- A tabu search tutorial based on a real-world scheduling problemCentral European Journal of Operations Research, 2010
- Multi-Objective Flexible Job-Shop Scheduling Problem in Steel Tubes ProductionSystems Engineering - Theory & Practice, 2009
- A heuristic to schedule flexible job-shop in a glass factoryEuropean Journal of Operational Research, 2005
- Hybrid evolutionary algorithm-based real-world flexible job shop scheduling problem: application service provider approachApplied Soft Computing, 2004
- Heuristic algorithms for unrelated parallel machine scheduling with a common due date, release dates, and linear earliness and tardiness penaltiesMathematical and Computer Modelling, 2001
- HEURISTICS FOR INTEGER PROGRAMMING USING SURROGATE CONSTRAINTSDecision Sciences, 1977