The Accuracy of Hybrid Estimating Approaches: A Case Study of an Australian State Road & Traffic Authority
Authors:
- 31 August 2010
- journal article
- research article
- Published by Taylor & Francis in The Engineering Economist
- Vol. 55 (3) , 225-245
Abstract
Reference class forecasting (RCF) is increasingly being adopted to mitigate two main factors causing persistent cost overruns in infrastructure projects—optimism bias and strategic misrepresentation. In practice, organizations tend to tailor generic estimating approaches to their unique operating environments by developing hybrid approaches blending RCF with other approaches such as the conventional fixed contingency approach. Yet, little empirical evidence exists on the accuracy of RCF or its variations. This study presents the results of estimation accuracy of a sample of road projects conducted by an Australian State Road & Traffic Authority using a hybrid estimating approach blending primarily RCF with fixed contingency approach. The results are then compared with historical results from literature on infrastructure projects and samples of two other dominant estimation methods, namely, the conventional fixed contingency approach and risk-based estimating (RBE). This study finds that the average accuracy of this sample using the hybrid approach compares favorably to historical results, which typically use the fixed contingency approach.Keywords
This publication has 23 references indexed in Scilit:
- Bias and Error in Mine Project Capital Cost EstimationThe Engineering Economist, 2008
- National and International Freight Transport Models: An Overview and Ideas for Future DevelopmentTransport Reviews, 2004
- Underestimating Costs in Public Works Projects:Error or Lie?Journal of the American Planning Association, 2002
- Big decisions, big risks. Improving accountability in mega projectsTransport Policy, 2002
- Twenty-one sources of error and bias in transport project appraisalTransport Policy, 1998
- Practices, barriers and benefits of using risk management approaches in selected Hong Kong industriesInternational Journal of Project Management, 1997
- Risk analysis and management in constructionInternational Journal of Project Management, 1997
- Project Evaluation and Uncertainty in Practice: A Statistical Analysis of Rate-of-Return Divergences of 1,015 World Bank ProjectsThe World Bank Economic Review, 1992
- A Comparison of Some Inflation, Growth and Unemployment ForecastsJournal of Economic Studies, 1988
- Prospect Theory: An Analysis of Decision under RiskEconometrica, 1979