Abstract
There are many benefits to reducing project delivery time by overlapping dependent activities. When considering the overlap of dependent design activities, one must also consider the consequences that may result from overlapping. Speeding up the design delivery process is not without risks or costs. Limiting the adverse consequences of overlapping requires a planning framework that appropriately evaluates overlapping strategies and the desired degree of overlap. The planning framework must also evaluate the consequences of overlapping dependent activities in terms of additional design and construction costs as well as the potential for rework. The large number of variables in the overlapping decision makes an analytical solution complex. After a review of analytical solutions to the overlapping problem, such as simulation and optimization, a basic decision algorithm is presented as an initial solution to this complex decision problem.