Mathematical Programming Application in Sublevel Caving Production Scheduling
Open Access
Abstract
Production scheduling determines the most beneficial mining sequence over the life of a mine. Developing a schedule that meets all mining aspects can substantially reduce mining costs and increase profitability. Among all underground mining methods, the sublevel caving method is a common method with moderate development requirements, a high production rate, and a high degree of mechanization and flexibility. None of the manual planning methods and heuristic algorithms used in commercial software will lead to a truly optimal schedule. Mathematical programming models, particularly mixed-integer programming (MIP), have been applied to provide an operationally feasible multi-time-period schedule in sublevel caving. However, confined blasting conditions, chaotic material flow, and frequent mixing of ore and waste while loading broken ore at the drawpoint make the sublevel caving method unique when producing a holistic plan. This paper reviews all mathematical programming models presented in sublevel caving production scheduling, highlights the inherent characteristics of the sublevel caving that affect production, and puts forward some promising ideas for future works.Keywords
This publication has 17 references indexed in Scilit:
- A multi-step approach for block-cave production scheduling optimizationInternational Journal of Mining Science and Technology, 2013
- Mixed-Integer Linear Programming formulation for block-cave sequence optimisationInternational Journal of Mining and Mineral Engineering, 2012
- A solution approach for optimizing long- and short-term production scheduling at LKAB’s Kiruna mineEuropean Journal of Operational Research, 2011
- A Review of Operations Research in Mine PlanningInterfaces, 2010
- Long-term open pit mine production planning: a review of models and algorithmsInternational Journal of Mining, Reclamation and Environment, 2008
- Using aggregation to optimize long-term production planning at an underground mineEuropean Journal of Operational Research, 2007
- The long-term mine production scheduling problemIIE Transactions, 2005
- Intelligent Modeling: Advances in Open Pit Mine Design and Optimization ResearchInternational Journal of Surface Mining, Reclamation and Environment, 2002
- Underground Planning at Stillwater Mining CompanyInterfaces, 2001
- An application of integer programming and simulation to production planning for a stratiform ore bodyMining Science and Technology, 1990