Holistic Framework for Highway Construction Cost Index Development Based on Inconsistent Pay Items
- 1 July 2021
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 147 (7) , 04021052
Abstract
A construction cost index (CCI) measures the price changes of construction items over time. It allows owner agencies and contractors to monitor construction market fluctuations so that they can more accurately estimate construction costs and project long-term funding needs. However, various CCI calculation methods in the highway construction industry are limited in two respects: (1) inability to account for inconsistent pay items, primarily caused by changes in pay item catalogs, and (2) insufficiency in statistically cleaning pay item data, e.g., unbalanced bid prices. For this reason, the resulting highway construction cost index (HCCI) cannot accurately reflect the construction market. To address such limitations, this research develops a three-step holistic framework for automated HCCI development using inconsistent pay items. The three-step methodology encompasses (1) data cleaning, where a text analysis algorithm and outlier detection algorithms are developed to clean inconsistent pay items and unbalanced bid prices; (2) pay item sampling, which helps to select and edit pay items through various statistical analysis; and (3) HCCI calculation, where the chained Fisher index formula is applied to calculate HCCIs at the state level, as well as indexes for specific regions and item categories. A prototype application is developed to generate quarterly and annual HCCIs automatically using the Python programming language. Ten-year data, i.e., 251,033 records, were used to verify and validate the prototyped system. The resulting HCCI and sub-HCCIs provide reliable insights into construction market conditions with high granularity. This research contributes to the body of knowledge by offering a holistic framework for automated HCCI development that leverages the text analysis algorithm for accounting for inconsistent pay items and two-stage outlier treatments for cleaning pay item data.Keywords
This publication has 19 references indexed in Scilit:
- Improving the Accuracy of Early Cost Estimates on Transportation Infrastructure ProjectsJournal of Management in Engineering, 2020
- Predicting the Volatility of Highway Construction Cost Index Using Long Short-Term MemoryJournal of Management in Engineering, 2020
- Analysis of the Variability of Submitted Unit Price Bids for Asphalt Line Items in Highway ProjectsJournal of Construction Engineering and Management, 2019
- Revised unit price practice in Turkish construction worksJournal of Construction Engineering, Management & Innovation, 2018
- Prediction of Unit Price Bids of Resurfacing Highway Projects through Ensemble Machine LearningJournal of Computing in Civil Engineering, 2018
- Generalized Autoregressive Conditional Heteroscedasticity Model to Quantify and Forecast Uncertainty in the Price of Asphalt CementJournal of Management in Engineering, 2017
- Time-Series Analysis for Forecasting Asphalt-Cement PriceJournal of Management in Engineering, 2017
- Current Practices of Highway Construction Cost Index Calculation and Utilization2016
- Volatility Forecast of Construction Cost Index Using General Autoregressive Conditional Heteroskedastic MethodJournal of Construction Engineering and Management, 2016
- A BAYESIAN APPROACH FOR FORECASTING ERRORS OF BUDGET COST ESTIMATESJOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2015