Abstract
This article presents the methodology and the criteria of ranging the actions based on defi nition of the modernization cost factor in network sections. It also shows the dependence of network development fi gures from key variables. The meth- odology refl ects the algorithm of calculation and conversion of initial action sheets to perform the ranging based on the cost and the reliability of network components related to the length of grids, section loads, annual average power supply inter- ruptions and power undersupply data. The results of target performance calculation for feeders with overhead transmission lines before and after modernization are provided with regard to its reliability parameters and the cost depending on section lengths. The action ranging is made by the minimum cost factor of the availability time increment (reduction of the power supply interruption time) by example of the feeder trunk section.