Abstract
During the 1st half of 2007, Heerema Marine Contractors will install the 20 inch Export SCR to the Independence Hub Facility, using Deepwater Construction Vessel Balder (figure 1). This 20 inch Export gas pipeline will be the deepest export pipeline installed to date and will be installed as part of the installation program of the Independence Hub Facility and SCRs. The offshore installation of the 20 inch Export SCR requires utilization of equipment to its maximum. Technical challenges involved are among others the pick-up of the SCR that has been pre-laid on top of four SCRs (2x8-inch, 2x10-inch), transfer of SCR from A&R Winch System to the Balder crane and reduction of loads on the SCR head during pull-in. This paper describes the most important issues of this SCR installation project, including methodologies specifically developed to deal with the technical challenges of this project. Introduction: On July 15th 2004, Enterprise Field Services, LLC awarded the contract for the installation of the floating production facility, Independence Hub, to Heerema Marine Contractors Nederland B.V (HMC). The Independence Hub Facility (IHUB) will be installed in Mississippi Canyon Block 920, in 8,000 ft of waterdepth. The Independence Trail Pipeline is the Export Gas Pipeline for the Independence Hub Facility. This pipeline system will initiate with the 20 inch diameter Export Steel Catenary Riser (SCR) on the IHUB. Part of HMC's scope is the installation of eight SCRs to the IHUB. Five 8 inch SCRs, two 10 inch SCRs and the 20 inch Export SCR. All pipelines, including SCRs have been constructed and temporarily stored, pre-laid, on the seabed (figure 2). Each SCR consists of steel pipe with an integrated flexjoint and a SCR head on the pipe end. Pre-installed on the SCRs are strakes and fairings to avoid vortex induced vibrations, a flex joint protective cover, flex tool, pipe flooding valves, hang-off collar and a pick-up rigging arrangement including buoy for installation purposes. After installation of the IHUB, the SCRs will be recovered and connected to the IHUB. The SCR installation will be done by HMC's Deepwater Construction Vessel (DCV) Balder. DCV Balder was built as Semi-Submersible Crane Vessel in 1978 and underwent an extensive life time extension and conversion program in 2001. [Ref 1] DCV Balder is specialized in installing complex deepwater field architecture and is well suited for the installation of the 20 inch Export SCR. Some characteristics of Balder equipment used for the SCR installation are:DP Class III, with a thrust capability of 350 mTDual crane capability, with deepwater capacity of 250 mT at 3000 m waterdepth.Mooring Line Deployment Winch (MLDW), with a capacity of 310 mT. (Static wire load including 12% dynamics) [ref 1]Abandonment and Recovery Winch System (A&R), with a hoisting capacity of 650 mT. [ref 2]. For the installation of a single pre-laid SCR to the IHUB, the following phases have been distinguished: