Recycling or landfill – Experience based on the example of Koralm Tunnel, contract KAT2 from design to construction
- 28 November 2017
- journal article
- research article
- Published by Wiley in Geomechanics and Tunnelling
- Vol. 10 (6) , 700-710
Abstract
The construction of the approx. 33 km long, twin‐bore Koralm Tunnel will produce about 5 million m3 of tunnel spoil. For this reason, a maximum degree of recycling of the material and landfill within the area of the three construction contracts were already intended at the start of design work. This had to consider optimal cost‐effectiveness of the entire materials management with minimal environmental impact through the minimising of transport journeys and areas exploited as well as the saving resources as far as possible. Specifically for the design of contract KAT2, the production and demand of material had to be compared from design to construction, taking into account the landfill and recycling possibilities while observing the technical constraints and the regulations concerning the chemical properties of waste.Keywords
This publication has 5 references indexed in Scilit:
- Responsible handling of tunnel spoil through the example of Koralm Tunnel contract KAT2 / Verantwortungsvoller Umgang mit Tunnelausbruch am Beispiel Koralmtunnel, Baulos KAT2Geomechanics and Tunnelling, 2015
- Recycling of tunnel excavation using the example of the Koralm Tunnel, contract KAT2 – Status April 2015 / Verwertung von Tunnelausbruch am Beispiel des Koralmtunnels, Baulos KAT2 – Stand April 2015Geomechanics and Tunnelling, 2015
- Tunnel excavation – The conflict between waste and recycling through the example of the Koralm Tunnel, contract KAT2 / Tunnelausbruch – Das Spannungsfeld zwischen Abfall und Verwertung am Beispiel Koralmtunnel, Baulos KAT2Geomechanics and Tunnelling, 2014
- Recycling of tunnel spoil – laws affecting waste from mining and tunnelling / Wiederverwertung von Tunnelausbruchmaterial – Abfallrecht im Berg‐ und TunnelbauGeomechanics and Tunnelling, 2011
- Solutions for the sustainable reduction of the tipping requirement at the Koralm tunnelGeomechanics and Tunnelling, 2009