Introducing the Dynamic Location Breakdown Structure: A Framework for Construction Sector Planning
Preprint
- 23 January 2026
- preprint
- Published by MDPI AG in Preprints.org
Abstract
Effective space management remains a fundamental yet frequently underestimated determinant of construction project success, as inadequate spatial planning leads to reduced productivity, congested work areas, inefficient resource movements, and elevated safety risks. This paper addresses the limitations of traditional static space-planning approaches by introducing the Dynamic Location Breakdown Structure (DLBS), a flexible, layered methodology for systematically organizing and dynamically updating construction sectors throughout project execution. The DLBS enables project managers to use architectural drawings and construction schedules to create structured representations of both interior and exterior sectors, organized into sequential layers that correspond to major construction stages—including preparatory work, excavation, structural erection, MEP installations, space division, finishing, and closure. Unlike conventional location breakdown structures that remain fixed throughout construction, the DLBS adapts to the evolving spatial configuration of the site as new areas emerge and existing sectors transform in response to structural progress, temporary installations, and resource deployments. For each defined sector, the methodology establishes four essential parameters: accessibility status (open, restricted access, temporary closure, or not accessible), maximum available area, occupied area, and remaining area. These parameters provide the informational foundation necessary for dynamic spatiotemporal calculations of occupancy rates within the broader Dynamic Modeling of Occupancy Rate Scheduling (DMORS) framework. By integrating DLBS with Chronographic Modeling \citep{Francis2004,Francis2016a, Francis2019a} principles, this research establishes a comprehensive approach to construction space management that enables proactive decision-making, resource optimization, congestion identification, and improved coordination among work crews throughout the construction lifecycle.Keywords
All Related Versions
This publication has 27 references indexed in Scilit:
- Parametric design methodology for developing BIM object libraries in construction site modelingAutomation in Construction, 2024
- Construction site layout planning problem: Past, present and futureExpert Systems with Applications, 2021
- Dynamic construction material layout planning optimization model by integrating 4D BIMEngineering with Computers, 2018
- Dynamic Multi-objective Layout Planning of Construction SitesProcedia Engineering, 2017
- A BIM-based automated site layout planning framework for congested construction sitesAutomation in Construction, 2015
- Construction site layout planning using multi-objective artificial bee colony algorithm with Levy flightsAutomation in Construction, 2014
- Dynamic construction site layout planning using max-min ant systemAutomation in Construction, 2010
- Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualisationAutomation in Construction, 2006
- Patterns of Construction-Space Use in Multistory BuildingsJournal of Construction Engineering and Management, 1995
- Modeling Work Space to Schedule Repetitive Floors in Multistory BuildingsJournal of Construction Engineering and Management, 1994