A conceptual design method of integrated equipment based on FBS: case study in GIS installation equipment
Authors:
- 16 December 2022
- conference paper
- Published by SPIE-Intl Soc Optical Eng
- Vol. 12500, 14-730
Abstract
GIS is a new type of substation equipment introduced into power grid construction which combines many components into one device. It is a typical representative of heavy equipment, but it requires higher stability during transportation and installation than others. The indoor space of GIS room is limited, and the ground condition is complex, so it is impossible to use large hoisting and transportation machines and tools. For the installation and transportation of GIS, the traditional manual handling is often inefficient and dangerous, and the traditional indoor crane cannot meet the requirements of GIS. Therefore, the research and development of indoor crane for GIS is needed, so this paper presents a new indoor crane for GIS on the basis of fully considering these requirements.Keywords
This publication has 8 references indexed in Scilit:
- A smart knowledge deployment method for the conceptual design of low-carbon productsJournal of Cleaner Production, 2021
- Research on Multi-Dimensional Information Service Oriented to Innovative Process Planning2021
- Supporting resilient conceptual design using functional decomposition and conflict resolutionAdvanced Engineering Informatics, 2021
- Stress and stability analysis of slewing motion for crawler crane mounted on flexible groundEngineering Failure Analysis, 2019
- The situated function-behavior-structure co-design modelCoDesign, 2019
- Reliability-based design optimization of crane bridges using Kriging-based surrogate modelsStructural and Multidisciplinary Optimization, 2019
- Extending the situated function–behaviour–structure framework to human–machine interactionInternational Journal on Interactive Design and Manufacturing (IJIDeM), 2015
- TRIZ 40 Inventive Principles Classification through FBS OntologyProcedia Engineering, 2015