Evaluation of loading and hauling technology for improving andesite mine performance
Authors:
Open Access
- 1 September 2018
- conference paper
- Published by IOP Publishing in IOP Conference Series: Materials Science and Engineering
- Vol. 403 (1) , 012048
Abstract
This paper evaluates the utilization of loading and hauling technology at andesite mine using cycle time and match factor methods. One mine site operated by PT. Anugerah Karya Agra Sentosa was taken as a case study. PT. Anugerah Karya Agra Sentosa located in Mujahiddin Village, Plampang Sub-district, West Sumbawa Regency is an andesite mining using open pit system with quarry type method. Mechanical equipment that operates is one unit Excavator (Kobelco SK 200) capacity 0.9 m3 and five units Dump Truck (Toyota Dyna 130 HT) with bucket capacity 3.6 m3. The analysis results found that the average cycle time for loading equipment was 0.54 minutes while the average cycle time for hauling equipment was 14.58 minutes. Recalculation for match factor (MF=1) resulted in additional of two hauling equipments from five units to seven units (Dump Truck).Keywords
This publication has 5 references indexed in Scilit:
- Application of a life cycle assessment to compare environmental performance in coal mine tailings managementJournal of Environmental Management, 2017
- Energy efficiency in mining: a review with emphasis on the role of operators in loading and hauling operationsJournal of Cleaner Production, 2016
- A framework for a sustainable approach to mine tailings management: disposal strategiesJournal of Cleaner Production, 2015
- The use of discrete event simulation for underground haulage mining equipment selectionInternational Journal of Mining and Mineral Engineering, 2014
- Energy and greenhouse gas impacts of mining and mineral processing operationsJournal of Cleaner Production, 2010