Setting planned lead times for a make-to-order production system with master schedule smoothing
Authors:
- 22 March 2011
- journal article
- research article
- Published by Taylor & Francis in IIE Transactions
- Vol. 43 (6) , 399-414
Abstract
This article considers a make-to-order manufacturing environment with fixed guaranteed delivery lead times and multiple product families, each with a stochastic demand process. The primary challenge in this environment is how to meet the quoted delivery times subject to fluctuating workload and capacity limits. The tactical planning parameters are considered, namely, the planning windows and planned lead times. The planning process that is modeled is the one in which the demand represents a dynamic input into the master production schedule. A planning window for each product family controls how the schedule of each product family is translated into a job release. It can be thought of as the slack that exists when the fixed quoted delivery lead time is longer than the total planned production lead time. Furthermore, the planned lead time of each station regulates the workflow within a multi-station shop. The model has underlying discrete time periods to allow the modeling of the planning process that is typically defined in time buckets; within each time period, the intra-period workflow that permits multiple job movements within the time period is modeled. The presented model characterizes key performance measures for the shop as functions of the planning windows and planned lead times. An optimization model is formulated that is able to determine the values of these planning parameters that minimize the relevant production-related costs. [Supplementary materials are available for this article. Go to the publisher's online edition of IIE Transactions for additional results of the simulation study in Section 6 of this manuscript.]Keywords
This publication has 20 references indexed in Scilit:
- Tractable Nonlinear Production Planning Models for Semiconductor Wafer Fabrication FacilitiesIEEE Transactions on Semiconductor Manufacturing, 2006
- An approximate planning model for distributed computing networksNaval Research Logistics (NRL), 2005
- Extensions to a tactical planning model for a job shop2003
- Workload based order release and productivity: a missing linkProduction Planning & Control, 2002
- A Dynamic Model for Requirements Planning with Application to Supply Chain OptimizationOperations Research, 1998
- Optimal Leadtimes Planning in a Serial Production SystemManagement Science, 1994
- Survey of scheduling research involving due date determination decisionsEuropean Journal of Operational Research, 1989
- A Tactical Planning Model for a Job ShopOperations Research, 1986
- Sequencing Rules and Due-Date Assignments in a Job ShopManagement Science, 1984
- A Study of Production Smoothing in a Job Shop EnvironmentManagement Science, 1984