Time Overrun in Public Works—Evidence from North-East Italy
Open Access
- 10 December 2019
- journal article
- research article
- Published by MDPI AG in Sustainability
- Vol. 11 (24) , 7057
Abstract
Cost and time overruns in public mega-projects have been widely studied and considered as interdependent factors in the literature on project management and the public economy. On the other hand, small-scale projects for public works (costing under €100 million) are far more common and contribute to transforming cities and territories even more than mega-projects. Is the development of these kinds of projects affected in the same way by overrun issues? Do cost and time overruns always go hand in hand? The present contribution tries to answer these questions by means of an empirical study on a dataset of 4781 small public works planned and built in the Veneto Region (north-east Italy) from 1999 to 2018. Specifically, the analysis refers to the stage of development when the decision is made to outsource the work, that is, after the project’s design and before its construction. Our sample of data is considered both as a whole and clustered by period, cost, contractor and category of work. The results of our analysis and statistical modeling are counterintuitive, suggesting that time overruns do not depend on the cost dimension, whereas norms and regulations play a crucial part in extending the duration of public works. The threshold by law of 1 million € costs implies time-consuming procedures to verify abnormal offers in the bid, that double the average award time from 244 days to 479 days.Keywords
Funding Information
- Department of Civil, Architectural and Environmental Engineering of the University of Padova (68/2018, prot. n. 560, date 29/03/2018)
This publication has 42 references indexed in Scilit:
- Three-Stage Least-Squares Analysis of Time and Cost Overruns in Construction ContractsJournal of Construction Engineering and Management, 2010
- Causes of delays in Saudi Arabian public sector construction projectsConstruction Management and Economics, 2009
- Estimating Cost Discrepancies in Highway Contracts: Multistep Econometric ApproachJournal of Construction Engineering and Management, 2008
- Managing public–private megaprojects: Paradoxes, complexity, and project designInternational Journal of Project Management, 2008
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- RETRACTED: Inaccuracy in Traffic ForecastsTransport Reviews, 2006
- Underestimating Costs in Public Works Projects:Error or Lie?Journal of the American Planning Association, 2002
- Big decisions, big risks. Improving accountability in mega projectsTransport Policy, 2002
- Factors influencing construction time and cost overruns on high-rise projects in IndonesiaConstruction Management and Economics, 1997
- The use of artificial neural networks in construction management: a reviewConstruction Management and Economics, 1996