Abstract
This paper presents a newly developed project monitoring and controlling method based on the synergy between project risk management (PRM) and earned value management (EVM). Its fundamental attribute is the introduction of the criticality index in EVM, which effectively models a dynamic aspect of the project frequently ignored in practice that is the existence of multiple critical paths. Two new stochastic indices are introduced, namely the weighted EAC