An empirical study of the complexity of requirements management in construction projects
Authors:
- Abdou Karim JallowAJAbdou Karim Jallow
- Peter DemianPDPeter Demian
- Andrew N. BaldwinABAndrew N. Baldwin
- Chimay AnumbaCAChimay Anumba
Open Access
- 9 September 2014
- journal article
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 21 (5) , 505-531
Abstract
Purpose: – The purpose of this paper is to investigate in-depth the current approach of managing client requirements in construction and to highlight the significant factors, which contribute to the complexity of managing the requirements in order to define a better approach. Design/methodology/approach: – A case study of a leading international global built asset and engineering consultancy organization was conducted over two years. The case study was conducted principally using semi-participant observations supplemented with other qualitative data collection methods (i.e. interviews, questionnaires and document analysis). Thematic analysis was used to analyze the data. Findings: – The results highlight major factors associated with the complexity of managing client requirements information, which include: mechanisms for documentation, storage and access, distribution of requirements information between stakeholders and across lifecycle phases of a project, traceability management and the provision of effective change management incorporating dependency checking and impact analysis. Research limitations/implications: – The main limitation of the research is the use of an in-depth study of a single organization, which applied the same project management method across all the projects they managed. Further work is planned to develop the proposed framework fully, and develop a software platform to operationalize and evaluate its industrial applicability with construction projects. Practical implications: – The implications of this research is that a better approach to managing requirements information is needed, which will facilitate the design, construction and operations of buildings within budget and time. An integrated framework and an associated tool are suggested to implement the approach. Originality/value: – This study identifies major research gaps and problems in the architecture, engineering, construction and facilities management industry; proposes and presents Electronic Requirements Information Management framework to facilitate lifecycle management of the requirements.Keywords
This publication has 32 references indexed in Scilit:
- Benefits realisation management: Panacea or false dawn?International Journal of Project Management, 2012
- Guide to Good Practice in the Management of Time in Complex Projects2010
- From hero to hubris – Reconsidering the project management of Heathrow’s Terminal 5International Journal of Project Management, 2010
- Requirements Engineering for Computer Integrated Environments in Construction2009
- Requirements management in practice: findings from an empirical study in the automotive industryResearch in Engineering Design, 2006
- Integrating product and process information in the construction sectorIndustrial Management & Data Systems, 2004
- Web‐based application for managing change orders in construction projectsConstruction Innovation, 2003
- Dilettantes, discipline and discourse: requirements management for constructionEngineering, Construction and Architectural Management, 2003
- Improving building design through integrated planning and controlEngineering, Construction and Architectural Management, 2002
- Collaborative design of structures using intelligent agentsAutomation in Construction, 2002