Linear Optimization Model to Minimize Total Cost of Repetitive Construction Projects and Identify Order of Units
- 1 July 2021
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Management in Engineering
- Vol. 37 (4) , 04021036
Abstract
This study developed a linear optimization model for scheduling repetitive construction projects with varying quantities of work in repetitive units. The model provides new capabilities that enable planners to identify an optimal/near-optimal schedule that minimizes project total cost and number of times crew work is interrupted. It is capable of identifying the optimal/near-optimal order of executing repetitive units to achieve further reduction in project time and cost. The model was developed in three main phases: (1) identifying input data such as quantities and crew productivity rates; (2) optimizing the construction schedule of repetitive units by identifying decision variables, formulating objective functions, and constraints, and executing model computations; and (3) visualizing the generated optimal/near-optimal schedule, crew interruption, project duration and cost, and order of executing repetitive units. Two case studies of 105 and 6 repetitive units were analyzed to evaluate the model performance. The model resulted in 0.13% and 4.2% additional reduction in project total cost and indirect cost, respectively, for the optimal order of repetitive units compared with the best model in the literature.Keywords
This publication has 52 references indexed in Scilit:
- Optimizing linear project scheduling with multi-skilled crewsAutomation in Construction, 2012
- Scheduling Repetitive Construction Projects Using Fuzzy Linear ProgrammingIOSR Journal of Mechanical and Civil Engineering, 2012
- Work Flow Variation and Labor Productivity: Case StudyJournal of Management in Engineering, 2011
- A genetic algorithm-based method for scheduling repetitive construction projectsAutomation in Construction, 2009
- Project scheduling problem with mixed uncertainty of randomness and fuzzinessEuropean Journal of Operational Research, 2007
- Optimization model for resource assignment problems of linear construction projectsAutomation in Construction, 2007
- Work Continuity Constraints in Project SchedulingJournal of Construction Engineering and Management, 2006
- Optimal Planning and Scheduling for Repetitive Construction ProjectsJournal of Management in Engineering, 2006
- Understanding the effect of the learning–forgetting phenomenon to duration of projects constructionInternational Journal of Project Management, 2001
- Resource-driven scheduling of repetitive activitiesConstruction Management and Economics, 1998