Risk analysis of the causes of time and cost overruns in the Lebanese precast industry
Authors:
Open Access
- 22 April 2026
- journal article
- research article
- Published by Frontiers Media SA in Frontiers in Built Environment
- Vol. 12, 1763749
Abstract
Introduction: The purpose of this article is to analyse the causes and risk behind time and cost overruns in the Lebanese precast sector, mainly hollow core slabs, precast beams and column. Methods: The methodology includes the following steps: (i) a review of the time and cost overrun causes in the global construction industry; (ii) the use of questionnaires to identify causes specific to the Lebanese precast industry; (iii) an examination of the significance, frequency, and impact of the causes; (iv) the ranking of the causes; and (v) the performance of quantitative risk analysis. Discussion: The most significant time overrun cause, according to research, is “Lack or delay of delivery of materials in markets”, while the most significant cost overrun cause is “Fluctuations in the cost of building materials”. The ranking results reveal a clear pattern: “financial management, contractual stability, and early design coordination” are the dominant determinants of both time and cost overruns in the Lebanese precast industry. According to the risk analysis study results, a project with a 50% risk level has a 37% time overrun potential and a 29% cost overrun potential. These findings imply that targeted interventions addressing the highest-probability causes can substantially reduce schedule risk, whereas cost control requires systemic and integrated strategies spanning design management, financial planning, contractual clarity, and market risk allocation. Conclusions: The primary causes of time and expense overruns in the Lebanese precast sector can be identified, ranked, and evaluated for risk by owners, project managers, and engineers thanks to this study. This study is the first to examine the causes that contribute to time and cost overruns in the precast concrete sector in Lebanon.Keywords
This publication has 41 references indexed in Scilit:
- Investigation of critical factors affecting cost overruns and delays in Egyptian mega construction projectsAlexandria Engineering Journal, 2023
- Analyzing delay causes in Egyptian construction projectsJournal of Advanced Research, 2014
- Ranking of delay factors in construction projects after Egyptian revolutionAlexandria Engineering Journal, 2013
- Analysing factors affecting delays in Indian construction projectsInternational Journal of Project Management, 2012
- Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countriesKSCE Journal of Civil Engineering, 2008
- Delays in construction projects: The case of JordanInternational Journal of Project Management, 2008
- Towards adoption of prefabrication in constructionBuilding and Environment, 2007
- Causes and effects of delays in Malaysian construction industryInternational Journal of Project Management, 2007
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- Large construction projects in developing countries: a case study from VietnamInternational Journal of Project Management, 2004