Abstract
Existing linear programming (LP) models of earthwork allocations in roadway construction assume that unit cost coefficients of earthwork activities and borrow pits/disposal sites capacities are certain and deterministic numbers. However in real-world problems there are naturally some uncertainties inherited in these values, which make it difficult to represent a single value as the candidate of entire possible values. This paper presents a fuzzy linear programming (FLP) model of earthwork allocations based on the fact of assuming unit cost coefficients and borrow pits/disposal sites capacities as fuzzy numbers while minimizing total earth-moving cost as an objective function. A method based on α cuts of a fuzzy set is used to take the uncertainty in borrow pits/disposal sites capacities into account. The uncertainty in fuzzy cost coefficients of the objective function and its effects on decision variables of the earthwork allocations model are also considered using the method presented by Chanas and Kucht...