Beam commissioning and operation of the Japan Proton Accelerator Research Complex 3-GeV rapid cycling synchrotron
Open Access
- 1 January 2012
- journal article
- research article
- Published by Oxford University Press (OUP) in Progress of Theoretical and Experimental Physics
- Vol. 2012 (1) , 2B003
Abstract
The 3-GeV rapid cycling synchrotron (RCS) of the Japan Proton Accelerator Research Complex (J-PARC) is a high-power pulsed proton driver aiming at 1 MW output beam power. The RCS was beam commissioned in October 2007 and made available for user operation in December 2008 with an output beam power of 4 kW. Since then, the output beam power of the RCS has been steadily increasing following progressions in beam tuning and hardware improvements. So far, the RCS has successfully achieved high-intensity beam trials of up to 420 kW at a low-level intensity loss of less than 1%, and the output beam power for the routine user program has been increased to 210 kW. The most important issues in increasing the output beam power are the control and minimization of beam loss to maintain machine activation within the permissible level. This paper presents the current status of the RCS beam power ramp-up, with particular emphasis on our approach to beam loss issues. The future prospects of RCS beam commissioning and operation are also described.Keywords
This publication has 9 references indexed in Scilit:
- Beam loss reduction by injection painting in the 3-GeV rapid cycling synchrotron of the Japan Proton Accelerator Research ComplexPhysical Review Special Topics - Accelerators and Beams, 2012
- First high-power model of the annular-ring coupled structure for use in the Japan Proton Accelerator Research Complex linacPhysical Review Special Topics - Accelerators and Beams, 2012
- Multiharmonic rf feedforward system for beam loading compensation in wide-band cavities of a rapid cycling synchrotronPhysical Review Special Topics - Accelerators and Beams, 2011
- Simulation of longitudinal beam manipulation during multi-turn injection in J-PARC RCSNuclear Instruments and Methods in Physics Research Section A: Accelerators, Spectrometers, Detectors and Associated Equipment, 2010
- Double-layer effects on the lifetime of newly developed HBC-foils for RCS of J-PARCNuclear Instruments and Methods in Physics Research Section A: Accelerators, Spectrometers, Detectors and Associated Equipment, 2009
- Direct observation of the phase space footprint of a painting injection in the Rapid Cycling Synchrotron at the Japan Proton Accelerator Research ComplexPhysical Review Special Topics - Accelerators and Beams, 2009
- Beam commissioning of the 3-GeV rapid cycling synchrotron of the Japan Proton Accelerator Research ComplexPhysical Review Special Topics - Accelerators and Beams, 2009
- Longitudinal painting with large amplitude second harmonic rf voltages in the rapid cycling synchrotron of the Japan Proton Accelerator Research ComplexPhysical Review Special Topics - Accelerators and Beams, 2009
- Efficiency simulations for the beam collimation system of the Japan Proton Accelerator Research Complex rapid-cycling synchrotronPhysical Review Special Topics - Accelerators and Beams, 2008