Practical and Successful Prevention of Annular Pressure Buildup on the Marlin Project
Authors:
- 1 September 2003
- journal article
- Published by Society of Petroleum Engineers (SPE) in SPE Drilling & Completion
- Vol. 18 (03) , 228-234
Abstract
Summary: In late 1999, BP plc experienced a well failure in the Marlin development in deepwater Gulf of Mexico. Within hours of starting production, the production tieback casing collapsed, causing failure of the production tubing. Pressurization of outer annuli because of production thermal effects was identified as the most likely cause of the failure.Keywords
This publication has 7 references indexed in Scilit:
- Marlin Failure Analysis and Redesign; Part 3, VIT Completion with Real-Time Monitoring2002
- Improve the Economics of Oil and Gas Wells by Reducing the Risk of Cement Failure2002
- Marlin Failure Analysis and Redesign; Part 2, Redesign2002
- Marlin Failure Analysis and Redesign; Part 1, Description of Failure2002
- Removing Subjective Judgment From Wettability Analysis Aids Displacement2000
- A Case Against Cementing Casing - Casing Annuli1996
- A New Method for the Relief of Annular Heat-Up Pressures1993