Improving Effectiveness of Constraints Removal in Construction Planning Meetings: Information-Theoretic Approach
Authors:
- 1 April 2020
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 146 (4)
Abstract
Timely identification and removal of constraints is critical for improving workflow reliability. Construction project managers need to spend a significant amount of working time in various types of planning meetings to discuss, analyze, and remove constraints. However, the amount of uncertainty associated with each constraint, mutual information shared among constraints, and any information gained by addressing those constraints are not necessarily known with any great accuracy or precision. This research used a bridge construction project as a case study to collect empirical data on detailed weekly meeting minutes over 18 weeks and the planned and actual starting and finish times of 475 activities. An information-theoretic approach was used to develop a framework to measure the amount of uncertainty and information sharing among constraint discussions. A Chow–Liu tree was then developed to help project managers optimize the sequence of topics discussed so that meeting time may be spent more productively. Results from this particular study indicate that weekly planning meetings need to strategically address issues of equipment availability, design and working method clarification, and prerequisite work readiness since removing those constraints could improve workflow reliability by 5.6%, 4.9%, and 3.6%, respectively. The contribution to the body of knowledge of this research was the development of a framework to utilize an information theoretic–based approach to measure information exchange, uncertainty, and sharing in construction planning meetings. The method can be applied to other construction projects, and the findings can help project managers plan and run meetings more effectively.Keywords
This publication has 25 references indexed in Scilit:
- Investigating the Cost-Benefit Trade-Off of Additional Planning Using Parade Game SimulationJournal of Management in Engineering, 2018
- Information theory-based approach for constructability assessment in truss structural systemsAutomation in Construction, 2017
- The use of information theory for the evaluation of biomarkers of aging and physiological ageMechanisms of Ageing and Development, 2017
- Removing Constraints to Make Tasks Ready in Weekly Work PlanningProcedia Engineering, 2016
- Using mutual information to capture major concerns of postural control in a tossing activityJournal of Biomechanics, 2015
- Effectiveness of Coordination Methods in Construction ProjectsJournal of Management in Engineering, 2014
- Informal interaction in construction progress meetingsConstruction Management and Economics, 2009
- Communication behaviour during management and design team meetings: a comparison of group interactionConstruction Management and Economics, 2007
- Information Theory and Neural Networks for Managing Uncertainty in Flood RoutingJournal of Computing in Civil Engineering, 2004
- Approximating discrete probability distributions with dependence treesIEEE Transactions on Information Theory, 1968