Incorporating geo-metallurgical information into mine production scheduling
Author:
- 1 January 2011
- journal article
- research article
- Published by Taylor & Francis in Journal of the Operational Research Society
- Vol. 62 (1) , 60-68
Abstract
Economic characterization of mining parcels depends upon geo-metallurgical properties, which vary throughout orebody. Mine production scheduling should aim to obtain maximum utility from orebody in suKeywords
This publication has 13 references indexed in Scilit:
- LP-based disaggregation approaches to solving the open pit mining production scheduling problem with block processing selectivityComputers & Operations Research, 2009
- Fundamental tree algorithm in optimising production scheduling for open pit mine designMining Technology: Transactions of the Institutions of Mining and Metallurgy, 2005
- How much would a blending stockpile reduce variation?Chemometrics and Intelligent Laboratory Systems, 2004
- Managing financial risk in planning under uncertaintyAIChE Journal, 2004
- An Application of Branch and Cut to Open Pit Mine SchedulingJournal of Global Optimization, 2003
- A new—old algorithm for minimum‐cut and maximum‐flow in closure graphsNetworks, 2001
- Conditional Indicator Simulation: Application to a Saskatchewan uranium depositMathematical Geology, 1984
- Optimal mine production scheduling: evaluation of large scale mathematical programming approachesGeotechnical and Geological Engineering, 1983
- A new theory of bed-blending derived from the theory of sampling — Development and full-scale experimental checkInternational Journal of Mineral Processing, 1981
- Application of Programs with Maximin Objective Functions to Problems of Optimal Resource AllocationOperations Research, 1974