Methodology of crane rail geometry control by geodetic measurements
Authors:
- Petko R. VranićPVPetko R. Vranić
- Jovan M. PopovićJPJovan M. Popović
- Milutin M. PejovićMPMilutin M. Pejović
- Branko Đ. MilovanovićBMBranko Đ. Milovanović
- Anastasija B. MartinenkoAMAnastasija B. Martinenko
Open Access
- 1 January 2023
- journal article
- research article
- Published by Centre for Evaluation in Education and Science (CEON/CEES) in Tehnika
- Vol. 78 (2) , 147-155
Abstract
In the new hall of the Institute for Materials and Structures, there was a need to control the geometry of the existing crane rails. In this paper, the methodology for determining the geometry of such a complex structure is presented, and the results of the applied method are also presented. The final product, i.e. the examined geometry of crane rails included numerical and graphical analysis of straightness, analysis of parallelism and analysis of horizontality of crane rails.Keywords
This publication has 7 references indexed in Scilit:
- Assessment the movement of the engineering structures within PANDA software packageTehnika, 2022
- Comparison of different measurement methods of crane runway2020
- Designing and realization of the control networks of the telecommunication tower AvalaTehnika, 2020
- Project of horizontal deplacement monitoring by geodetic methods at the part of supporting wall of the E75 motorwayTehnika, 2019
- Control Measurements of Crane Rails Performed by Terrestrial Laser ScanningSensors, 2017
- An Alternative Approach to Control Measurements of Crane RailsSensors, 2012
- Automated Measurement System for Crane Rail Geometry DeterminationProceedings of the 37th International Symposium on Automation and Robotics in Construction (isarc), 2010