Construction Scheduling Using the Constraint Satisfaction Problem Method
- 1 April 2013
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 139 (4) , 414-422
Abstract
Construction projects are subject to numerous constraints of various types, including contractual due dates, resource limitations, and safety, financial, and managerial constraints. Most scheduling methods based on the critical path method (CPM) require that all project constraints be comprehensively defined and arranged into a single logical network for developing a project schedule. In real-life situations, however, there could be more than one option of execution, conditions, and/or precautions that may influence the logic of the project network and its outputs. CPM-based methods have been proven inadequate for scheduling in this kind of situation. This paper views construction scheduling as a constraint satisfaction problem (CSP), which is defined by a set of scheduling variables and a set of constraints. A CSP-based scheduling method has been developed to provide a framework for systematic constraint modeling and effective schedule generation. An illustrative real-life case example is present...Keywords
This publication has 19 references indexed in Scilit:
- PDM++: Planning Framework from a Construction Requirements PerspectiveJournal of Construction Engineering and Management, 2011
- Prediction System for Change Management in Construction ProjectJournal of Construction Engineering and Management, 2010
- Improved genetic algorithm for resource-constrained scheduling of large projectsCanadian Journal of Civil Engineering, 2009
- Float Consumption Impact on Cost and Schedule in the Construction IndustryJournal of Construction Engineering and Management, 2007
- Application of Dependency Structure Matrix for Activity Sequencing in Concurrent Engineering ProjectsJournal of Construction Engineering and Management, 2006
- Optimization of Resource Allocation and Leveling Using Genetic AlgorithmsJournal of Construction Engineering and Management, 1999
- WorkPlan: Constraint-Based Database for Work Package SchedulingJournal of Construction Engineering and Management, 1999
- Implementation of resource constraints in ILOG SCHEDULE: a library for the development of constraint-based scheduling systemsIntelligent Systems Engineering, 1994
- Criticism of CPM for Project Planning AnalysisJournal of Construction Engineering and Management, 1984
- Maintaining knowledge about temporal intervalsCommunications of the ACM, 1983