Abstract
This paper demonstrates development of a controller-hardware-in-the-loop test system for validating microgrid control schemes. The investigation also proposes and analyzes the performance of an IEC 61850 Generic Object-Oriented Substation Event Protocol (GOOSE) based control strategy for managing the transition of a microgrid test model from grid connected mode to island mode. The test model contains a single inverter-interfaced distributed energy resource (DER). The inverter controls allow the DER to regulate its output during grid connected operation and regulate the microgrid voltage and frequency when separated from the Area Electric Power System. The test model, inverter and microgrid controllers are simulated using RTDS Technologies' real-time digital simulator. A Digital protection relay is used in the hardware loop to provide I/O to the simulated controllers via GOOSE messaging. The results of the investigation illustrate the benefits of IEC 61850 standard for integration of controller hardware in a microgrid control scheme as well as the suitability of GOOSE messaging for seamless transitioning between microgrid operating modes.
Funding Information
  • U.S. Department of Energy
  • Energy Efficiency and Renewable Energy's Advanced Manufacturing Office (DE-EE0008409)

This publication has 23 references indexed in Scilit: