Simulating Uncertainties in Construction Projects with Chronographical Scheduling Logic
Authors:
- Adel Francis<&Sol;AAdel Francis<&Sol;A
- & Sol; Spanph& Period; D& Period;<& Sol; Span&S& Sol; Spanph& Period; D& Period;<& Sol; Span
Open Access
- 1 January 2017
- journal article
- research article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 143 (1)
Abstract
The more complex a project, the more attractive nontraditional project delivery methods like design-build or fast-tracking become with these delivery methods and uncertainty has to be explicitly integrated into the network calculations. Uncertainties assess levels of compliance with various constraints. This paper contributes to the existing body of knowledge by modeling diverse types of execution uncertainties, such as construction operation, execution process, and work with doubtful results, and by extending the traditional logic and modeling uncertainties using the chronographic time-scaled, point-to-point relations, production-based dynamic relations, and function dependencies between in-progress activities. The dependencies between activities can be related to the external scale (usually representing time) or an internal scale (usually representing quantity). Using the Monte Carlo simulation, the paper simulates the impact of construction operations, execution processes, and work with doubtful results. For companies, this approach represents scheduling constraints in a flexible manner and provides a feasible solution for modeling the complexity of real-world projects.Keywords
This publication has 18 references indexed in Scilit:
- Simulation of scheduling logic using dynamic functionsProceedings of the Institution of Civil Engineers - Management, Procurement and Law, 2013
- A chronographic method for construction project planningCanadian Journal of Civil Engineering, 2006
- Critical Path Method with Multiple CalendarsJournal of Construction Engineering and Management, 2005
- Decision Support for Project Management using A Chronographic ApproachJournal of Decision Systems, 2002
- Statistical dependence in risk analysis for project networks using Monte Carlo methodsInternational Journal of Production Economics, 1999
- Generalised models of design interation using signal flow graphsResearch in Engineering Design, 1997
- A Model-Based Framework to Overlap Product Development ActivitiesManagement Science, 1997
- Network Scheduling Techniques for Construction Project Management1997
- Time-uncertainty analysis in project networks with a new merge-event time-estimation techniqueInternational Journal of Project Management, 1993
- Letter to the Editor—Attempts to Validate Certain PERT Statistics or “Picking on PERT”Operations Research, 1962