Studi Kelayakan Pembangkit Listrik Hybrid Energi Terbarukan di Pulau Moyo Kab. Sumbawa

Authors:
  • ISImam Syaukani
    Imam Syaukani
  • MMMuhammad Agil Fadhlan M
    Muhammad Agil Fadhlan M
  • HNHalid Nuryadi
    Halid Nuryadi

Abstract
The increasing global demand for electricity has driven the transition from limited fossil energy sources to more environmentally friendly renewable energy. This study aims to evaluate the feasibility of a hybrid power generation system (HPGS) combining wind and solar energy in Labuan Aji Village, Moyo Island, Sumbawa. Using Homer Pro software, the analysis includes simulation, optimization, and economic evaluation of the HPGS. The results indicate that the system can generate a total energy output of 54,715 kWh per year, with a renewable energy penetration rate of 69.13%. The HPGS is deemed feasible for implementation to sustainably meet the community's electricity needs. This study provides a practical solution for renewable energy development in remote areas