Abstract
Conceptual cost estimating is typically completed early in the project lifecycle when little design work has been completed. Because little information is known at this early stage, the estimate usually deviates substantially from the actual construction cost. When expressed as a deterministic value, an estimate often leads to a false inference of accuracy by those not familiar with the vagaries of conceptual cost estimating, making it difficult for an agency to explain cost growth. A stochastic conceptual estimate allows an agency to produce a probability distribution of the likely construction costs and address the level of confidence in a given estimate. Named probability distributions are readily available for developing a stochastic estimate in a great deal of commercial software. However, instead of fitting available distributions, this research generates an empirical distribution to express a cost estimate range. Creating empirical distributions eliminates assumptions required for selecting...Keywords
This publication has 23 references indexed in Scilit:
- Reducing Data-Collection Efforts for Conceptual Cost Estimating at a Highway AgencyJournal of Construction Engineering and Management, 2016
- Value-Added Decision Making for Managers2011
- A Framework for Guaranteed Maximum Price and Contingency Development for Integrated Delivery of Transportation ProjectsJournal of Construction Engineering and Project Management, 2011
- Relating Cost Growth from the Initial Estimate to Design Fee for Transportation ProjectsJournal of Construction Engineering and Management, 2007
- Quantity-Based Approach to Preliminary Cost Estimates for Highway ProjectsTransportation Research Record: Journal of the Transportation Research Board, 2006
- Underestimating Costs in Public Works Projects:Error or Lie?Journal of the American Planning Association, 2002
- Bootstrap re-sampling for unbalanced data in supervised learningEuropean Journal of Operational Research, 2001
- Probabilistic Risk Analysis2001
- Bootstrap Methods and their Application1997
- An Introduction to the Bootstrap1993