Uncertainty is often the most significant source of risk associated with a project in tunnel and underground construction. Unforeseen uncertainties can lead to significant construction problems leading to reduced tunnel advances and delays, cost increases, damage to existing infrastructure and/or damage to building equipment. The M5 metro line, which is the subject of the study, is located in Uskudar – Umraniye - Cekmekoy - Sancaktepe district on the Asian side of Istanbul. The line is approximately 17.5 km long and has 16 cut and cover stations. M5 metro line was used the four earth pressure balance (EPB) tunnel boring machines. The effect of uncertainty on risk assessment and decision-making is increasingly given priority, particularly for large infrastructure projects such as tunnels where uncertainty is often the primary source of risk. This article is intended to explain the tangible benefits of underground uncertainty and risk assessment of the M5 metro construction for underground project stakeholders, local authorities, designers, practitioners and researchers.Keywords
Funding Information
- no (no)
This publication has 27 references indexed in Scilit:
- Decision tree analysis for project risk mitigation options for underground metro rail projectInternational Journal of Decision Sciences, Risk and Management, 2012
- Risk analysis during tunnel construction using Bayesian Networks: Porto Metro case studyTunnelling and Underground Space Technology, 2012
- Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBMTunnelling and Underground Space Technology, 2009
- Geotechnical risk assessment based approach for rock TBM selection in difficult ground conditionsTunnelling and Underground Space Technology, 2008
- Ground behaviour and rock mass composition in underground excavationsTunnelling and Underground Space Technology, 2008
- Key points of contention in framing assumptions for risk and uncertainty managementInternational Journal of Project Management, 2006
- Industrial accidents: Challenges for China’s economic and social developmentSafety Science, 2005
- Model for Estimation of Time and Cost for Tunnel Projects Based on Risk EvaluationRock Mechanics and Rock Engineering, 2005
- Modelling TBM performance with artificial neural networksTunnelling and Underground Space Technology, 2004
- Safety evaluation of engineering and construction projects in ChinaJournal of Loss Prevention in the Process Industries, 2003