Application of the DEMATEL method for quantitative analysis of risk factors for railway investments in Poland
Open Access
- 23 May 2024
- journal article
- research article
- Published by Public Library of Science (PLoS) in PLOS ONE
- Vol. 19 (5) , e0303606
Abstract
The paper presents the results of research on the influence of risk factors on the implementation of railway investments in Poland (build stage) and deals with a detailed diagnosis of relation between factors. The application of DEcision MAking Trial and Evaluation Laboratory (DEMATEL) method for the analyses allowed to develop a cause-and-effect model of key factors and analyse the importance of the factors. Eleven factors identified in eariel studies as the most important risk factors were examined. It was found that the factors: errors in the preparation of tender documents (10.38%), errors in project documentation (10.02%), improperly estimated time of completion of the investment by the Employer (9.82%), internal regulations of PKP Polskie Koleje Państwowe S.A. (Polish State Railways) not coordinated with the provisions of contracts (9.51%) have the highest degree of importance. Factors: too many external institutions involved in the investment process and internal regulations of PKP Polskie Koleje Państwowe S.A. (Polish State Railways) not coordinated with the provisions of contracts, have the greatest net impact on the other factors. The relations between the factors and factors importance are valuable knowledge for engineers, enabling the project to be implemented according to the planned schedule and investment cost.Keywords
This publication has 29 references indexed in Scilit:
- Risk factors for delays in rail investments implemented in the Design & Build contractsMATEC Web of Conferences, 2019
- Multiphase Assessment of Project Risk Interdependencies: Evidence from a University ISD Project in TaiwanProject Management Journal, 2016
- Assessing relative importance and mutual influence of barriers for CCS deployment of the ROAD project using AHP and DEMATEL methodsInternational Journal of Greenhouse Gas Control, 2015
- Identifying and assessing critical risk factors for BIM projects: Empirical studyAutomation in Construction, 2014
- An integrated indicator framework for spatial assessment of industrial and social vulnerability to indirect disaster lossesNatural Hazards, 2013
- Analysing factors affecting delays in Indian construction projectsInternational Journal of Project Management, 2012
- Delays in construction projects: The case of JordanInternational Journal of Project Management, 2008
- Causes and effects of delays in Malaysian construction industryInternational Journal of Project Management, 2007
- Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case studyInternational Journal of Project Management, 2003
- Construction delays in a fast-growing economy: Comparing Thailand with other economiesInternational Journal of Project Management, 1996