Difficulties in driving offshore piles to design penetrations are not infrequent and result in costly delays. Some of the more frequent problems are illustrated by six case histories of long piles driven to penetrations from 200 to 300 ft in various offshore regions. Drivability of the installed piles for each of these cases was investigated in retrospect by the one-dimensional wave equation, a technique that can also be applied as an important step in preconstruction planning. The need for supplemental procedures to aid pile driving because of unfavorable installation conditions can frequently be anticipated from combined evaluation of wave equation results and practical pile driving experience. Supplemental pile installation procedures such as jetting and pre-drilling should be performed under close engineering supervision to assure that the completed pile installation is consistent with design requirements. Introduction: Fixed platforms have been built in waters as deep as 400 ft for drilling and producing offshore oil and gas fields, and in shallower waters of 50 to 100 £t for lighthouse structures and deep-sea terminals. Most of the platforms are of the template-type construction that is shown in Fig. 1(a). A tubular steel space frame or substructure is placed on the ocean floor, and then open-end pipe piles are driven through the main vertical or slightly battered members into the foundation soils. The piles are typically 30-in. to 48-in. in diameter. Another type of platform that has been used in regions where structures are exposed to severe storms, or to strong currents, or to large ice loads is illustrated in Fig. 1(b). These tower platforms have relatively few large diameter legs and incorporate a circular group of piles. The open-end pipe piles are driven through pipe sleeves attached either internally or externally to the large diameter legs. In addition to axial operating loads, offshore structures are subjected to large horizontal loads from waves and currents, and possibly from ice and earthquakes. Under combined vertical and horizontal loading conditions, piles in deep water requiring ultimate compressive and tensile capacities of up to 3500 and 2000 tons, respectively, are installed to penetrations of about 200 to 350 ft. Penetrations of about 400 ft have been required at some locations, and total pile lengths have been almost 800 ft. In the marine construction industry, difficulties in driving piles to design penetrations are frequently experienced and can create uncertainty in axial pile capacities and pastille deficiency in flexural capacity. Efforts to deal with driving problems when they arise are time consuming and therefore, costly because of expensive derrick barge rentals. If procedures to aid pile driving are improperly applied, then such procedures may lead to questionable adequacy of the platform foundation. Planning for driving offshore piles utilizing the one-dimensional wave theory is outlined in this paper, and supplemental installation procedures to aid driving are described. The effectiveness and the limitations of pile-driving systems and supplemental installation procedures are illustrated by six case histories