Enhancing project success: the impact of sociotechnical integration on project and program management using earned value management systems
Open Access
- 27 February 2024
- journal article
- research article
- Published by Emerald Publishing in International Journal of Managing Projects in Business
- Vol. 17 (8) , 1-21
Abstract
Purpose: Earned value management systems (EVMS), also called integrated project and program management systems, have been greatly examined in the literature, which has typically focused on their technical aspects rather than social. This study aims to hypothesize that improving both the technical maturity of EVMS and the social environment elements of EVMS applications together will significantly impact project performance outcomes. For the first time, empirical evidence supports a strong relationship between EVMS maturity and environment.Design/methodology/approach: Data was collected from 35 projects through four workshops, attended by 31 industry practitioners with an average of 19 years of EVMS experience. These experts, representing 23 organizations, provided over 2,800 data points on sociotechnical integration and performance outcomes, covering projects totaling $21.8 billion. Statistical analyses were performed to derive findings on the impact of technical maturity and social environment on project success.Findings: The results show statistically significant differences in cost growth, compliance, meeting project objectives and business drivers and customer satisfaction, between projects with high EVMS maturity and environment and projects with poor EVMS maturity and environment. Moreover, the technical and social dimensions were found to be significantly correlated.Originality/value: Key contributions include a novel and tested performance-driven framework to support integrated project management using EVMS. The adoption of this detailed assessment framework by government and industry is driving a paradigm shift in project management of some of the largest and most complex projects in the U.S.; specifically transitioning from a project assessment based upon a binary approach for EVMS technical maturity (i.e. compliant/noncompliant to standards) to a wide-ranging scale (i.e. 0–1,000) across two dimensions.Keywords
This publication has 47 references indexed in Scilit:
- Rising with the machines: A sociotechnical framework for bringing artificial intelligence into the organizationJournal of Business Research, 2020
- Integration of Social Capital and Organizational Learning Theories to Improve Operational PerformanceGlobal Journal of Flexible Systems Management, 2019
- Complex socio-technical systems: Characterization and management guidelinesApplied Ergonomics, 2015
- Perceived causes of software project failures – An analysis of their relationshipsInformation and Software Technology, 2014
- Advancing socio-technical systems thinking: A call for braveryApplied Ergonomics, 2014
- Perspectives on research in project management: the nine schoolsGlobal Business Perspectives, 2013
- Project Management with Dynamic Scheduling2013
- History, Practices, and Future of Earned Value Management in Government: Perspectives from NASAProject Management Journal, 2012
- Analyzing project management research: Perspectives from top management journalsInternational Journal of Project Management, 2009
- Key project management practices affecting Singaporean firms’ project performance in ChinaInternational Journal of Project Management, 2009