Identification and Ranking of Factors Affecting the Delay Risk of High-Rise Construction Projects Using AHP and VIKOR Methods
Open Access
- 31 January 2024
- journal article
- research article
- Published by MDPI AG in Infrastructures
- Vol. 9 (2) , 24
Abstract
Construction projects, especially those for commercial purposes, require thorough planning and control to ensure success within predetermined budgets and timelines. This research, conducted in Mashhad, Iran, employs the analytic hierarchy process (AHP) and VIKOR methods to identify and rank factors influencing delays in high-rise projects. The study, based on a sample of 40 projects, emphasizes the comprehensive nature of our research method. The scale for features in project selection includes societal importance (with different applications including cultural hubs, affordable housing initiatives, and urban renewal for social equity), size (less and more than 20 units in residential projects), and diversity (mixed-use development, inclusive infrastructure, and cultural and recreational spaces), contributing to a comprehensive analysis of construction delays. Expert project managers and engineers provided insights through two questionnaires, and their responses underwent thorough analysis. Our findings not only underscore the significance of factors contributing to project success but also rank their impact on the likelihood of delays. The study reveals that the negative effects of these factors on cost, time, and project quality vary. Time emerges as the most influential parameter, with approximately six times more impact on cost and nine times more on quality. Contractor financial weakness, delays in allocating financial and credit resources, insufficient project resource allocation, contractor technical and executive weakness, and a lack of proper implementation and project control are identified as the most important factors contributing to delays.Keywords
Funding Information
- Technical University of Liberec (SGS-2024-3471, LM2023066)
- Czech Republic’s Ministry of Education, Youth, and Sports (SGS-2024-3471, LM2023066)
This publication has 38 references indexed in Scilit:
- Importance and ranking evaluation of delay factors for development construction projects in BeninKSCE Journal of Civil Engineering, 2013
- An Empirical Study of Schedule Delay Causes Based on Taiwan's Litigation CasesProject Management Journal, 2013
- Project management approaches for dynamic environmentsInternational Journal of Project Management, 2009
- Delay Analysis within Construction Contracting OrganizationsJournal of Construction Engineering and Management, 2008
- Delays in construction projects: The case of JordanInternational Journal of Project Management, 2008
- Causes of delay in large construction projectsInternational Journal of Project Management, 2006
- Large construction projects in developing countries: a case study from VietnamInternational Journal of Project Management, 2004
- Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case studyInternational Journal of Project Management, 2003
- Material and equipment procurement delays in highway projects in NepalInternational Journal of Project Management, 2002
- Causes of construction delay: traditional contractsInternational Journal of Project Management, 2002