A Genetic Algorithm for the Proactive Resource-Constrained Project Scheduling Problem With Activity Splitting
- 4 July 2018
- journal article
- research article
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Engineering Management
- Vol. 66 (3) , 459-474
Abstract
Proactive scheduling aims at the generation of robust baseline schedules, which has been studied for many years with the assumption that activity splitting is not allowed. In this paper, we focus on the proactive resource-constrained project scheduling problem in which each activity can be split at discrete time instants under the constraints of a maximum number of splitting and a minimum period of continuous execution. In this problem, setup times are also considered. A mathematical model is established and analyzed, of which two properties and one lemma are proposed. As the problem is proved to be${\text{NP}}$-hard in the strong sense, for solving the model, we develop a genetic algorithm (GA) in which the two proposed properties and the lemma are applied as local search operators. After linearizing the proposed model, we use a commercial mathematical programming solver as a benchmark to solve the problem. From the computational results, we find that the developed GA is effective and efficient in solving the defined problem, and activity splitting improves robustness. With the growth of the maximum number of splitting, the decline in the minimum execution time, the decrease in the setup times, and the extension of the project due date, robustness increases.Keywords
Funding Information
- China Scholarship Council (201606280246)
- National Natural Science Foundation of China (71371150, 71572138, 71732006, 71390331, 71572148, 71742005)
This publication has 36 references indexed in Scilit:
- Proactive policies for the stochastic resource-constrained project scheduling problemEuropean Journal of Operational Research, 2011
- Time slack-based techniques for robust project scheduling subject to resource uncertaintyAnnals of Operations Research, 2010
- Proactive heuristic procedures for robust project scheduling: An experimental analysisEuropean Journal of Operational Research, 2008
- Linear programming based algorithms for preemptive and non-preemptive RCPSPEuropean Journal of Operational Research, 2007
- Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splittingEuropean Journal of Operational Research, 2006
- The trade-off between stability and makespan in resource-constrained project schedulingInternational Journal of Production Research, 2006
- Stability and resource allocation in project planningIIE Transactions, 2004
- Robust and reactive project scheduling: a review and classification of proceduresInternational Journal of Production Research, 2004
- PSPLIB - A project scheduling problem libraryEuropean Journal of Operational Research, 1997
- An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problemEuropean Journal of Operational Research, 1996