Construction Cost and Duration Uncertainty Model: Application to High-Speed Rail Line Project
Authors:
- 1 October 2016
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 142 (10)
Abstract
Transportation construction projects are often plagued by cost overruns and delays. Applying contingencies and estimating risks at the project level often do not capture the multiple uncertainties in the construction process of large transportation projects. Thus, there is a need for innovative approaches and tools to avoid large construction cost and duration overruns. To counteract such underestimations, a construction model and an uncertainty model are developed. In the construction model, the construction of the four main types of structures in rail lines (tunnels, viaducts, cuts, and embankments) is modeled bottom-up from the single activity to the entire rail line. In the uncertainty model, three sources of uncertainty (variability in the construction process, correlations between the costs of repeated activities, and disruptive events) are modeled jointly at the level of the single activity. In a Monte Carlo simulation environment, these uncertainties are propagated to the total constructio...Keywords
This publication has 28 references indexed in Scilit:
- Policy and Planning for Large-Infrastructure Projects: Problems, Causes, CuresEnvironment and Planning B: Planning and Design, 2007
- Using fuzzy risk assessment to rate cost overrun risk in international construction projectsInternational Journal of Project Management, 2007
- Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoningBuilding and Environment, 2004
- Decision Aids for Tunneling: UpdateTransportation Research Record: Journal of the Transportation Research Board, 2004
- Underestimating Costs in Public Works Projects:Error or Lie?Journal of the American Planning Association, 2002
- APRAM: an advanced programmatic risk analysis methodInternational Journal of Technology, Policy and Management, 2001
- A proposal for construction project risk assessment using fuzzy logicConstruction Management and Economics, 2000
- The validity of the triangular distribution assumption in Monte Carlo simulation of construction costs: empirical evidence from Hong KongConstruction Management and Economics, 1995
- An agenda for cost modelling researchConstruction Management and Economics, 1991
- Predicting the Tender Price of Buildings during Early Design: Method and ValidationJournal of the Operational Research Society, 1984