On the relocation problem with a second working crew for resource recycling
Authors:
- 15 January 2006
- journal article
- research article
- Published by Taylor & Francis in International Journal of Systems Science
- Vol. 37 (1) , 27-34
Abstract
In this paper, we introduce a variant of the relocation problem, which was formulated from a public house redevelopment project in Boston. In the problem of interest, given some initial resources in a common pool there is a set of jobs to be processed on a two-machine flowshop. Each job acquires a specific number of resources to start its processing and will return a number of resources to the pool at its completion. The resource consumption and resource recycle processes are performed on machine one and machine two, respectively, in a two-machine flowshop style. Abiding by the resource constraints, the problem seeks to find a feasible schedule whose makespan is minimized. In this paper, we first present NP-hardness proofs for some special cases. Three heuristic algorithms are designed to compose approximate schedules. Two lower bounds are developed and then used to test the performance of our proposed heuristics. Numerical results from computational experiments suggest that the proposed heuristics can produce quality solutions in a reasonable time.Keywords
This publication has 12 references indexed in Scilit:
- Minimizing the weighted number of tardy jobs and maximum tardiness in relocation problem with due date constraintsEuropean Journal of Operational Research, 1999
- Polynomial algorithms for single machine scheduling problems with financial constraintsOperations Research Letters, 1997
- Generating the best K sequences in relocation problemsEuropean Journal of Operational Research, 1993
- Some results of the relocation problems with processing times and deadlinesInternational Journal of Computer Mathematics, 1991
- A fast feasibility test for relocation problemsEuropean Journal of Operational Research, 1988
- Relocation problems are hardInternational Journal of Computer Mathematics, 1988
- Relocation models for public housing redevelopment programsEnvironment and Planning B: Planning and Design, 1986
- Scheduling subject to resource constraints: classification and complexityDiscrete Applied Mathematics, 1983
- Optimization and Approximation in Deterministic Sequencing and Scheduling: a Survey1979
- Optimal two‐ and three‐stage production schedules with setup times includedNaval Research Logistics Quarterly, 1954