Integrating numerical tools in underground construction process
Authors:
- 3 July 2009
- journal article
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 16 (4) , 376-391
Abstract
Purpose – The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and uncertainties encountered while the execution is underway. Design/methodology/approach – A case study on the construction of a metro station is used as a pilot project to show the effectiveness of replacing traditional construction processes by more innovative procedures. Concurrent engineering (CE) is applied to optimize the execution time of the underground structure. A numerical simulation is integrated into the construction process in order to update design parameters with real site conditions observed during the construction process. Findings – The results show that the implementation of CE is efficient in reducing the completion time, with an 18 per cent reduction observed in this case study. A cost reduction of 20 per cent on the steel frame support and a total cost reduction of 3 per cent were obtained. Research limitations/implications – The study demonstrates that the application of CE methods can be quite valuable in large, complex construction projects. Vulgarizing it as “the solution” to adjust time frame delay, control quality and cost, might be an issue for local construction enterprises in Algeria. Originality/value – Using the concept of CE by overlapping different activities involved in a construction project and making use of simulation tools in the process at different stages of the execution have resulted in modifying the excavation method and hence reducing the completion times.Keywords
This publication has 17 references indexed in Scilit:
- Dynamic change management for construction: introducing the change cycle into model‐based project managementSystem Dynamics Review, 2003
- Integrating Concurrent Engineering Concepts in a Steelwork Construction ProjectConcurrent Engineering, 2000
- Situational Reengineering: Case Study AnalysisJournal of Construction Engineering and Management, 2000
- Design and engineering process integration through a multiple view intermediate modeller in a distributed object-oriented system environmentComputer-Aided Design, 1998
- Concurrent Engineering: A Schedule Reduction ToolJournal of Construction Engineering and Management, 1997
- Simultaneous engineering approach to an integrated design and process planningEuropean Journal of Operational Research, 1997
- Concurrent Engineering in the Construction IndustryConcurrent Engineering, 1997
- Concurrent engineering in design-build projectsConstruction Management and Economics, 1997
- Book Review : Concurrent Engineering Fundamentals, Volume I, Authored by Biren Prasad; Published by Prentice Hall, 1 Lake Street, Upper Saddle River, NJ 07458, 1996, ISBN 0-13-147463-4Concurrent Engineering, 1996
- Value of Concurrent Engineering for A/E/C IndustryJournal of Management in Engineering, 1994