Active BIM Approach to Optimize Work Facilities and Tower Crane Locations on Construction Sites with Repetitive Operations
Open Access
Abstract
This paper presents an active building information modeling (BIM) approach for work facilities and the optimal positioning of tower cranes on construction sites with repetitive operations. In this context, the metamorphosis of a passive BIM approach into an active approach is described. Here, the enhancement of the construction-ready BIM model starts with the export of the optimization input parameters, such as the 3D coordinates of the building, perimeter of the construction site, space for feasible solutions, relevant segment of the building with repetitive works, etc. Depending on the complexity of the problem, the user selects a suitable optimization approach and formulates the tower crane positioning optimization problem with the objective of minimizing the total duration of the operation’s cycle. Similarly, according to the model formulation, the user also chooses the optimization tool, including the search algorithm. The final step involves the post-optimal analysis and importing of the optimal solution into the BIM. An application example is demonstrated at the end of the paper to show the advantages of the proposed approach in which the optimization model has significantly improved the initial solution of the crane and depot positions.Keywords
This publication has 20 references indexed in Scilit:
- A BIM-based approach for automated tower crane layout planningAutomation in Construction, 2015
- GA optimization model for solving tower crane location problem in construction sitesAlexandria Engineering Journal, 2015
- BIM-Based Construction Scheduling Method Using Optimization Theory for Reducing Activity OverlapsJournal of Computing in Civil Engineering, 2015
- Supporting Decision-Making in the Building Life-Cycle Using Linked Building DataBuildings, 2014
- Framework for Work-Space Planning Using Four-Dimensional BIM in Construction ProjectsJournal of Construction Engineering and Management, 2014
- Integrating BIM and GIS to improve the visual monitoring of construction supply chain managementAutomation in Construction, 2013
- Productivity and CO2 emission analysis for tower crane utilization on high-rise building projectsAutomation in Construction, 2013
- Development of a BIM-based structural framework optimization and simulation system for building constructionComputers in Industry, 2012
- Assessing the Environmental Impacts of a Lean Supply System: Case Study of High-Rise Condominium Construction in KoreaJournal of Architectural Engineering, 2010
- Cranes for Building Construction ProjectsJournal of Construction Engineering and Management, 2007