Minimum performance bounds for evaluating contractors performance during construction of highway pavement projects
- 29 April 2008
- journal article
- research article
- Published by Taylor & Francis in Construction Management and Economics
- Vol. 26 (5) , 507-529
Abstract
For project control during construction, evaluating the performance of contractors is usually established through progress measurement that compares the actual performance to the planned performance. Corrective actions and/or performance penalties are then established as relative measures that judge the actual performance based on current project plans without considering the performance of other similar projects or the lowest performance that projects could reach while still being successful. To establish a generalized benchmark measure and a non‐project‐specific project control tool, the concept of minimum performance bounds is explained in relation to their development for highway pavement projects. The bounds were developed using constrained‐parameters polynomial regression and cluster analysis for a sample of 497 highway pavement projects in Washington State. Minimum bounds for small, medium and large projects were fairly distinguishable signifying the project size effect on the location and shape of performance bounds. Bounds were also developed for projects classified by asphalt quantities, contract values, project duration and project length, being the common criteria used by highway agencies. Owners would use the minimum performance bounds as control tools when requesting corrective actions, establishing incentives, imposing performance penalties, initiating a default clause for substandard performance, and/or in pre‐qualifying contractors for new projects.Keywords
This publication has 18 references indexed in Scilit:
- A novel multiple linear regression model for forecasting S‐curvesEngineering, Construction and Architectural Management, 2006
- Probabilistic Forecasting of Project Performance Using Stochastic S CurvesJournal of Construction Engineering and Management, 2004
- Model on cash flow forecasting and risk analysis for contracting firmsInternational Journal of Project Management, 2002
- Probabilistic Monitoring of Project Performance Using SS-CurvesJournal of Construction Engineering and Management, 2000
- How Many Subjects Does It Take To Do A Regression AnalysisMultivariate Behavioral Research, 1991
- Developing and Implementing C?SCSCJournal of Professional Issues in Engineering Education and Practice, 1991
- A construction project cash flow model—an idiographic approachConstruction Management and Economics, 1986
- Cost Control: Integrated Cost/Schedule PerformanceJournal of Management in Engineering, 1986
- Earned Value Technique for Performance MeasurementJournal of Management in Engineering, 1985
- Modelling capital expenditureEngineering and Process Economics, 1979