4 Years history: From 2D to BIM for CH: The main spire on Milan Cathedral
- 1 September 2012
- conference paper
- Published by Institute of Electrical and Electronics Engineers (IEEE)
- p. 377-382
Abstract
The paper presented describes the final step of four years survey activities on Milan Cathedral. The main aim of the job was to survey and model the big spire to support restoration works that had just started. The last stage was to transform the great model into a 3D WEB BIM to help manage and organize restoration works.Keywords
This publication has 3 references indexed in Scilit:
- INTEGRATED STRATEGIES FOR THE MODELING VERY LARGE AND COMPLEX ARCHITECTURESThe International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences, 2012
- Surveying and modelling the main spire of Milan Cathedral using multiple data sourcesThe Photogrammetric Record, 2011
- The Meaning of BIM2008