Displacement-Based Back-Analysis of the Model Parameters of the Nuozhadu High Earth-Rockfill Dam
Open Access
- 1 January 2014
- journal article
- research article
- Published by Wiley in The Scientific World Journal
- Vol. 2014, 1-10
Abstract
The parameters of the constitutive model, the creep model, and the wetting model of materials of the Nuozhadu high earth-rockfill dam were back-analyzed together based on field monitoring displacement data by employing an intelligent back-analysis method. In this method, an artificial neural network is used as a substitute for time-consuming finite element analysis, and an evolutionary algorithm is applied for both network training and parameter optimization. To avoid simultaneous back-analysis of many parameters, the model parameters of the three main dam materials are decoupled and back-analyzed separately in a particular order. Displacement back-analyses were performed at different stages of the construction period, with and without considering the creep and wetting deformations. Good agreement between the numerical results and the monitoring data was obtained for most observation points, which implies that the back-analysis method and decoupling method are effective for solving complex problems with multiple models and parameters. The comparison of calculation results based on different sets of back-analyzed model parameters indicates the necessity of taking the effects of creep and wetting into consideration in the numerical analyses of high earth-rockfill dams. With the resulting model parameters, the stress and deformation distributions at completion are predicted and analyzed.Keywords
Funding Information
- National Natural Science Foundation of China (51209118, 51179092, 51379103, 2013-KY-4)
- National Natural Science Foundation of China (51209118, 51179092, 51379103, 2013-KY-4)
- National Natural Science Foundation of China (51209118, 51179092, 51379103, 2013-KY-4)
- State Key Laboratory of Hydroscience and Engineering (51209118, 51179092, 51379103, 2013-KY-4)
This publication has 12 references indexed in Scilit:
- An intelligent displacement back-analysis method for earth-rockfill damsComputers and Geotechnics, 2007
- A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling – Illustrated with a case studyTunnelling and Underground Space Technology, 2006
- A new displacement back analysis to identify mechanical geo‐material parameters based on hybrid intelligent methodologyInternational Journal for Numerical and Analytical Methods in Geomechanics, 2004
- On measuring creep behaviour in granular materials through triaxial testingCanadian Geotechnical Journal, 2002
- Using genetic algorithms to select architecture of a feedforward artificial neural networkPhysica A: Statistical Mechanics and its Applications, 2001
- Combining a neural network with a genetic algorithm for process parameter optimizationEngineering Applications of Artificial Intelligence, 2000
- Identification of parameters for air permeability of shotcrete tunnel lining using a genetic algorithmComputers and Geotechnics, 1999
- Implicit constitutive modelling for viscoplasticity using neural networksInternational Journal for Numerical Methods in Engineering, 1998
- Nonlinear Analysis of Concrete Face Rockfill DamJournal of Geotechnical Engineering, 1990
- Back analysis of measured displacements of tunnelsRock Mechanics and Rock Engineering, 1983