Automated Schedule and Cost Control Using 3D Sensing Technologies
Open Access
- 5 January 2023
- journal article
- research article
- Published by MDPI AG in Applied Sciences
- Vol. 13 (2) , 783
Abstract
Nowadays, many construction projects in KSA still struggle with cost overruns and delay in activities. Therefore, automatic monitoring approaches are needed in the construction progress monitoring domain (CPM) to address these concerns. Thus, this paper proposed a system integrating a BIM-planned model with site laser scans, as laser scanners showed massive potential in the CPM domain. The algorithms of the proposed system recognized 3D objects based on the intersection between models, alignment accuracy, and Lalonde features. The proposed system combined 3D object recognition technology with 5D information data into a 5D progress tracking system using earned value (EV) principles. The reason behind that is a lack of research regarding conducting a 5D assessment integrated BIM with 3D sensing technology in the CPM domain. The proposed system was verified using field data from a superstructure construction project where the object recognition indicators showed a 98% recall and 99% precision in recognizing 3D objects. The proposed system also used a color-coding system to address the condition of each element based on its recognition and scheduling state and address any occlusions while calculating the recognized objects. The results also revealed an automatically updated status of the project’s progress in terms of schedule(4D) and cost(5D). The automated results were also validated with a manual calculation, where a slight variation (1.35%) was observed between those calculations. This system demonstrates a degree of accurate progress tracking, automatically exceeding manual performance with less computational time.Keywords
Funding Information
- King Saud University, Riyadh, Saudi Arabia (RSP2023R264)
This publication has 42 references indexed in Scilit:
- Vision-based material recognition for automated monitoring of construction progress and generating building information modeling from unordered site image collectionsAdvanced Engineering Informatics, 2014
- Multi-criteria analysis of Projects' performance in constructionArchives of Civil and Mechanical Engineering, 2014
- Automated progress control using laser scanning technologyAutomation in Construction, 2013
- DIMENSIONALITY BASED SCALE SELECTION IN 3D LIDAR POINT CLOUDSThe International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences, 2012
- Automated progress tracking using 4D schedule and 3D sensing technologiesAutomation in Construction, 2012
- Plane-based registration of construction laser scans with 3D/4D building modelsAdvanced Engineering Informatics, 2012
- Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC IndustryLeadership and Management in Engineering, 2011
- Automated Recognition of 3D CAD Objects in Site Laser Scans for Project 3D Status Visualization and Performance ControlJournal of Computing in Civil Engineering, 2009
- Natural terrain classification using three‐dimensional ladar data for ground robot mobilityJournal of Field Robotics, 2006
- Ladars for construction assessment and updateAutomation in Construction, 2000