Do public–private partnerships achieve better time and cost performance than regular contracts?
Open Access
- 29 April 2020
- journal article
- other
- Published by Taylor & Francis in Public Money & Management
- Vol. 41 (4) , 286-295
Abstract
Infrastructure development with public–private partnership (PPP) contracts has been claimed to lead to better performance compared to regular contracts. However, the empirical evidence for this claim is weak. The authors assessed the difference in the actual performance of Dutch infrastructure PPP projects (design–build–finance–maintain: DBFM) compared to regularly procured projects (design-and-construct: D&C). DBFM projects demonstrated significantly better cost performance. Public–private partnerships (PPPs) have been widely used for the development and management of transport infrastructure, such as highways, railways, and waterways. However, hard evidence that PPPs perform better than regularly procured projects is lacking. Existing evidence tends to rely on anecdotal and perceptual data. This paper provides policy-makers and managers with real information about the actual performance and benefits of PPPs.Keywords
This publication has 38 references indexed in Scilit:
- Comparative performance of PPPs and traditional procurement projects in IndonesiaInternational Journal of Public Sector Management, 2017
- A Comparative Analysis and Evaluation of Specialist PPP Units’ Methodologies for Conducting Value for Money AppraisalsJournal of Comparative Policy Analysis: Research and Practice, 2016
- Different cost performance: different determinants?Transport Policy, 2012
- Comparison of Public–Private Partnerships and Traditional Procurement Methods in North American Highway ConstructionTransportation Research Record: Journal of the Transportation Research Board, 2012
- Risks and the financing of PPP: Perspectives from the financiersThe British Accounting Review, 2011
- Alternative Project Delivery Methods for Water and Wastewater Projects: Do They Save Time and Money?Leadership and Management in Engineering, 2011
- Fixing the contract after the contract is fixed: A study of incomplete contracts in IT and construction projectsInternational Journal of Project Management, 2011
- A Brief Intellectual History of the Public–Private Partnership Movement2010
- Towards a Principal-Agent Based Typology of Risks in Public-Private PartnershipsIMF Working Papers, 2009
- Improved PFI/PPP service outcomes through the integration of Alliance principlesInternational Journal of Project Management, 2006