Abstract
This paper analyses information loss (data drop) in the handover between design phases of BIM-based railway infrastructure projects, framed by the Brazilian National Logistics Plan (PNL) and the BIM BR Strategy. The problem lies in the informational fragmentation observed in practice and documented in the literature. The objective is to analyze how different procurement models condition this flow. The method is a hypothesis-driven critical literature review, with the construction of an analytical matrix as a synthesis artefact relating for procurement models (DBB, DB, EPC, and IPD) to four hypotheses of informational inefficiency (H1 – H4). DBB presents the highest risk of data drop, due to sequential fragmentation; DB and EPC retain a medium risk when BIM is treated as complementary; IPD is the most aligned to BIM, although its effectiveness depends on clear requirements and legal recognition. The contribution lies in the proposed matrix, which makes explicit how contractual decisions condition information flow and recommends mechanisms to mitigate data drop.