The analyses and performance of a soldier-pile-tremie-concrete (SPTC) wall with a significant unbraced length is presented. The wall was constructed as part of the excavation support system of the Ramp D tunnel jacking pit built for Contract C09A4 of the Central Artery/Tunnel Project in Boston, Massachusetts. This wall is unique in that it supported a cut with a height of approximately 19.5 m (64 ft) with only two brace levels above the subgrade with a clear span between the subgrade and lower brace level of 14.3 m (47 ft) above the excavation subgrade. The excavation subgrade consisted of Boston Blue Clay, the top 6.4 m (21 ft) of which was improved by jet grouting within the footprint of the jacking pit. The SPTC wall was also designed to resist train loads located about 6.1m (20 ft) behind the wall. The SPTC wall was socketed into the Boston argillite bedrock. Other prominent features of this support wall include the structural details of the two internal braces. The upper level brace consisted of a horizontal steel truss, while the lower level brace was a 4.88-m(16-foot)-wide, 1.22-m(4-foot)-deep post-tensioned reinforced concrete beam. Details of these two braces are described herein. The behavior of the wall was predicted using SOILSTRUCT during the design phase. A comparison of the predicted and measured wall deflections is provided.