Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem
- 11 November 2019
- journal article
- research article
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- Vol. 27 (4) , 893-916
Abstract
Purpose: Construction firms keep minimal resources to maintain productive working capital. Hence, resources are constrained and have to be shared among multiple projects in an organization. Optimal allocation of resources is a key challenge in such situations. Several approaches and heuristics have been proposed for this task. The purpose of this paper is to compare two approaches for multi-mode resource-constrained project scheduling in a multi-project environment. These are the single-project approach (portfolio optimization) and the multi-project approach (each project is optimized individually, and then heuristic rules are used to satisfy the portfolio constraint).Design/methodology/approach: A direct search algorithm called Probabilistic Global Search Lausanne is used for schedule optimization. Multiple solutions are generated that achieve different trade-offs among the three criteria, namely, time, cost and quality. Good compromise solutions among these are identified using a multi-criteria decision making method, Relaxed Restricted Pareto Version 4. The solutions obtained using the single-project and multi-project approaches are compared in order to evaluate their advantages and disadvantages. Data from two sources are used for the evaluation: modified multi-mode resource-constrained project scheduling problem data sets from the project scheduling problem library (PSPLIB) and three real case study projects in India.Findings: Computational results prove the superiority of the single-project approach over heuristic priority rules (multi-project approach). The single-project approach identifies better solutions compared to the multi-project approach. However, the multi-project approach involves fewer optimization variables and is faster in execution.Research limitations/implications: It is feasible to adopt the single-project approach in practice; realistic resource constraints can be incorporated in a multi-objective optimization formulation; and good compromise solutions that achieve acceptable trade-offs among the conflicting objectives can be identified.Originality/value: An integer programming model was developed in this research to optimize the multiple objectives in a multi-project environment considering explicit resource constraints and maximum daily costs constraints. This model was used to compare the performance of the two multi-project environment approaches. Unlike existing work in this area, the model used to predict the quality of activity execution modes is based on data collected from real construction projects.Keywords
This publication has 41 references indexed in Scilit:
- Multi‐criteria decision making for collaborative design optimization of buildingsBuilt Environment Project and Asset Management, 2011
- A survey of variants and extensions of the resource-constrained project scheduling problemEuropean Journal of Operational Research, 2010
- Resource-constrained multi-project scheduling: Priority rule performance revisitedInternational Journal of Production Economics, 2010
- Scheduling of multiple projects with resource transfersInternational Journal of Mathematics in Operational Research, 2009
- Two-phase heuristics for scheduling of multiple projectsInternational Journal of Operational Research, 2009
- A genetic algorithm for the resource constrained multi-project scheduling problemEuropean Journal of Operational Research, 2008
- Factors influencing project delivery within construction clients’ multi‐project environmentsEngineering, Construction and Architectural Management, 2004
- Development and application of a hybrid genetic algorithm for resource optimization and managementEngineering, Construction and Architectural Management, 2002
- An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flowsConstruction Management and Economics, 2002
- A decomposition approach to multi-project schedulingEuropean Journal of Operational Research, 1991