Dynamic Spatiotemporal Scheduling for Construction Building Projects
Open Access
Abstract
For building projects, the manager is responsible for coordinating the work of subcontractors at the construction site. This includes operations, material flows, and storage. In summary, one of their main roles is to ensure smooth team rotation, maintain fluid circulation, and avoid congestion or relaxation on the site. However, traditional tools lack the ability to consider the planning and management of worksite spaces when calculating the execution schedule and critical path. Consequently, three-week planning is usually carried out separately on independent plans, often using spreadsheets. In addition, a construction site is highly dynamic and mobile in nature, and the positioning of resources and workers can change daily. This makes the management of available space even more complex, and effective space management becomes an imperative. To address this challenge, this paper develops visual dynamic artifacts that present different operation types. The methodology and the conceptual framework facilitate the calculation of the Occupancy Rate (OR) that enables construction project managers to create simple yet dynamic spatiotemporal models of the construction schedule. By incorporating factors such as crew turnover and occupancy evolution, managers can simplify the calculation process and effectively optimize construction work by utilizing site occupancy rates. In summary, this paper presents the Dynamic Model of the Occupancy Rate Schedule (DMORS), a methodology developed through design science. This model utilizes created artifacts representing various operation types to ensure accurate calculations of dynamic occupancy by floor and sector in a site. Consequently, it enables the construction of a more realistic schedule based on critical space ideologies. The DMORS enables managers to use the OR for different floors and sectors of a site, allowing for better space management. A proof of concept demonstrates that this tool can enhance the efficiency and productivity of construction projects by optimizing crew schedules and resource allocation based on site OR.Keywords
This publication has 21 references indexed in Scilit:
- 4D-BIM Dynamic Time–Space Conflict Detection and Quantification System for Building Construction ProjectsJournal of Construction Engineering and Management, 2018
- The Concept of Float Calculation Based on the Site Occupation using the Chronographical LogicProcedia Engineering, 2017
- Float Types in Construction Spatial SchedulingJournal of Construction Engineering and Management, 2016
- Optimal utilization of interior building spaces for material procurement and storage in congested construction sitesAutomation in Construction, 2013
- Quantification of Spatial Temporal Congestion in Four-Dimensional Computer-Aided DesignJournal of Construction Engineering and Management, 2010
- Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualisationAutomation in Construction, 2006
- Identification and Resolution of Work Space Conflicts in Building ConstructionJournal of Construction Engineering and Management, 2002
- Space Planning Method for Multistory Building ConstructionJournal of Construction Engineering and Management, 1997
- SCaRC: Space-Constrained Resource-Constrained Scheduling SystemJournal of Computing in Civil Engineering, 1997
- Patterns of Construction-Space Use in Multistory BuildingsJournal of Construction Engineering and Management, 1995