This paper makes a practice-based critique of the assumptions behind network planning methods from the perspective of subcontractors and suppliers. In the context of a case example, the time-cost trade-off and its resource-oriented extensions are critiqued as being incapable of representing the capacity costs and constraints of subcontractors and suppliers. These methods are also critiqued as being incapable of representing the effects of site conditions on productivity, which in turn affects the capacity choices of subcontractors. Restricting the focus to the general building industry, case findings from 15 subcontractors and suppliers are presented. The case research indicates that capacity constraints systematically affect subcontractors and suppliers and that site conditions affect the productivity of subcontractors. Moreover, it is found that these firms consistently take action to mitigate the impact of capacity constraints and site conditions on cost. This second finding suggests that not only do n...Keywords
This publication has 15 references indexed in Scilit:
- Product costing for complex manufacturing systemsInternational Journal of Production Economics, 1998
- Scheduling Projects with Repeating ActivitiesJournal of Construction Engineering and Management, 1998
- Patterns of Construction-Space Use in Multistory BuildingsJournal of Construction Engineering and Management, 1995
- An economic view of project coordinationConstruction Management and Economics, 1995
- Bidding Strategy: Winning over Key CompetitorsJournal of Construction Engineering and Management, 1992
- The Development of the Construction Engineer: Past Progress and Future ProblemsJournal of Construction Engineering and Management, 1991
- Building Theories from Case Study ResearchAcademy of Management Review, 1989
- Relevant costs, congestion and stochasticity in production environmentsJournal of Accounting and Economics, 1988
- Is construction project planning really doing its job? A critical examination of focus, role and processConstruction Management and Economics, 1987
- Construction Planning—Beyond the Critical PathJournal of the Construction Division, 1980