A scatter search heuristic for maximising the net present value of a resource-constrained project with fixed activity cash flows
- 16 March 2009
- journal article
- Published by Taylor & Francis in International Journal of Production Research
- Vol. 48 (7) , 1983-2001
Abstract
In this paper, we present a meta-heuristic algorithm for the resource-constrained project scheduling problem with discounted cash flows. We assume fixed payments associated with the execution of project activities and develop a heuristic optimisation procedure to maximise the net present value of a project subject to the precedence and renewable resource constraints. We investigate the use of a bi-directional generation scheme and a recursive forward/backward improvement method from literature and embed them in a meta-heuristic scatter search framework. We generate a large dataset of project instances under a controlled design and report detailed computational results. The solutions and project instances can be downloaded from a website in order to facilitate comparison with future research attemptsKeywords
This publication has 30 references indexed in Scilit:
- Principles of scatter searchEuropean Journal of Operational Research, 2006
- A bidirectional heuristic for maximizing the net present value of large‐scale projects subject to limited resourcesNaval Research Logistics (NRL), 2003
- An integrated survey of deterministic project schedulingOmega, 2001
- Phase transitions in project schedulingJournal of the Operational Research Society, 1999
- Resource-constrained project scheduling: Notation, classification, models, and methodsEuropean Journal of Operational Research, 1999
- An optimal procedure for the resource-constrained project scheduling problem with discounted cash flows and generalized precedence relationsComputers & Operations Research, 1998
- The development of cash flow weight procedures for maximizing the net present value of a projectJournal of Operations Management, 1996
- A survey on the resource-constrained project scheduling problemIIE Transactions, 1995
- Project scheduling: The effects of problem structure on heuristic performanceNaval Research Logistics Quarterly, 1976
- The payment scheduling problemNaval Research Logistics Quarterly, 1972